The Government of Spain improved WWTP connection with irrigators Molina Campotéjar (03/11/2009)

The president of the Hydrographic Confederation of Segura (CHS), José Salvador Fuentes Zorita, visited, with the mayor of Molina de Segura, Eduardo Contreras, works to improve the connection between the Sewage Treatment Station (STP) of Molina de Segura and the raft of regulation Campotéjar irrigators.

The work, budgeted at EUR 998,627.48, are being implemented by the CHS by the Special Fund for the Revitalisation of the Economy and Employment (Plan E), managed by the Ministry of Environment and Rural and Marine Affairs, and have been declared emergency.

The performance impact will be felt in four municipalities, as the Community Irrigation Campotéjar with farmers not only in Molina de Segura, but also Archena Lorquí and Ulea.

The work will affect all the existing infrastructure of service between the treatment plant and reservoir, and that includes work on the point of arrival of water to the irrigation system, piping and the reception raft.

All these facilities were outdated and in some cases new ones were needed, as raised by the body's own basin irrigation.

Therefore, the improvement is the connection of pipes with a arquetón, the commissioning of pumping equipment and a line of medium voltage power supply first.

On the other hand, building a processing center and placed in a trench several sections of GRP pipes and PAD.

And finally it is the process of cleaning and replacement of waterproofing sheet raft of receipt of the drive.

Source: CHS

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información